Dove Bank Primary School, Nailstone
It took 2 days and 19 flat bed trucks to deliver 2 classrooms, a hall extension, group room and new staff room for Dove Bank Primary School. Sounds easy enough, but a lot of background work by the design team took place to ensure that all the factory built components fitted exactly to the existing, with millimetre precision. Looking forward to seeing the extension being finished off together with some internal alterations, ready for the new school year. #school #progress #pri

Progress at Hall Orchard CE Primary School
The two new classrooms for Hall Orchard are almost complete, but there are also extensive external works taking place as part of this project. A previously underused, awkwardly sloping area of the playground is being transformed into an amphitheatre, to provide seating for 60 children. This will give the school a new outdoor classroom facility - weather permitting. #school #progress #primary #site #visit #hallorchard

Teaching future generations to swim
Planning permission has been granted for a refurbished and extended swimming pool at Church Hill C of E Junior School, Leicestershire. A training pool was originally built on the school site in the 1960s'. In the last few years however, due to the broken boiler and poor state of the building, it was decided that it was no longer fit for use. The school hope to revive the much missed pool and replace the old building with one that has modern facilities and the latest equipmen